Traffic management on Wood End Lane, Fradley
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-3-09/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Fradley
- Contractor
- BBV JV
- Type of works
- Construction
- Estimated Start Date
- 23/05/2022
- Estimated End Date
- 03/06/2022
What we are doing
BBV will be installing temporary traffic lights and lane closures for a length of 200m in five locations, on Wood End Lane. This is to allow us to safely carry out the installation of signage, to highlight works access points and provide advance warning of works traffic.
Our works will commence on Monday 23 May, for a two week duration. Working hours will be from 8am until 6pm Monday to Friday. Access to properties will always be maintained.