Skip to main page content
View route map

Traffic rerouting around Northway Island commences Monday 26 April for four weeks and two hour closure on B4438 between 12am and 2am on the 26 April 2021

Work item: HS2-EW-LM-Ph1-Int-St-N3-Prog-works-29-20/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Solihull, West Midlands
Location
Bickenhill
Contractor
LM JV
Type of works
Traffic management
Estimated Start Date
26/04/2021
Estimated End Date
23/05/2021

What we are doing

Traffic rerouting around Northway Island will commence from 5am on Monday 26 April for four weeks. During the next four weeks, short sections of Northway Island will be closed. As a result, road users will no longer be able to travel around the whole of the Island. Depending on your direction of travel, you may be redirected from Northway Island and back to access routes either side of the M42.

Direction of travel along the B4438, A452 and Northway will be unaffected, and you will still be able to access all routes in the area.

During this four week period, we will maintain free flowing traffic, as well as access to all buildings and businesses in the area.

To safely carry out activities in preparation for traffic rerouting to commence on Monday 26 April, sections of the B4438 will also be closed from 12 midnight to 2am on Monday 26 April. A signed diversion route will be in place for drivers.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]