Trial holes on Hampstead Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-23/05/2025

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road
Contractor
SCS JV
Type of works
Trial Holes
Estimated Start Date
16/06/2025
Estimated End Date
30/06/2025

What we are doing

To inform the design of our utility works on Hampstead Road and ensure the route below is clear, we need to survey an area south of
Robert Street, close to the pedestrian crossing.

From 16 to 30 June Monday to Friday 8am to 6pm we will dig a trial hole in the eastern footpath and partially within MDjv’s (Mace Dragados) site boundary on Hampstead Road.

We will partially close the footpath and maintain pedestrian access at all times. We will hand dig, survey, and then reinstate the area.
There may be some periods of increased noise as we complete this work. We apologise for any disruption these works may cause.