Truggist Lane, plant crossing opening, Berkswell
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-6-07/09/2021/NC
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Berkswell
- Worksite Name
- Truggist Lane
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 15/11/2021
- Estimated End Date
- 31/10/2024
What we are doing
Following the completion of our Plant Crossing in October 2021 we will begin operating the crossing using a temporary traffic light system to allow construction traffic to safely cross the lane. The lights will be sequenced as normal for the low bridge and will be set to all red when a site vehicle approaches to cross the lane. The lights will be operational from 8.00am to 6.00pm Monday to Friday, 08.00am to 1.00pm Saturday.
The Plant crossing will be operational from 16 November 2021 to October 2024 and will only be used when necessary.
There will be advanced warning signs placed on Truggist Lane and Station Road for the traffic lights and we will also keep you updated through www.hs2insolihull.co.uk .