Skip to main page content
View route map

Truggist Lane, plant crossing opening, Berkswell

Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-6-07/09/2021/NC

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
Berkswell
Worksite Name
Truggist Lane
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
15/11/2021
Estimated End Date
31/10/2024

What we are doing

Following the completion of our Plant Crossing in October 2021 we will begin operating the crossing using a temporary traffic light system to allow construction traffic to safely cross the lane. The lights will be sequenced as normal for the low bridge and will be set to all red when a site vehicle approaches to cross the lane. The lights will be operational from 8.00am to 6.00pm Monday to Friday, 08.00am to 1.00pm Saturday.

The Plant crossing will be operational from 16 November 2021 to October 2024 and will only be used when necessary.

There will be advanced warning signs placed on Truggist Lane and Station Road for the traffic lights and we will also keep you updated through www.hs2insolihull.co.uk .

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]