Tunnel segment deliveries at Willesden Euroterminal site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Traf-1-09/10/24
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Old Oak Lane, Victoria Road
- Worksite Name
- Flat Iron site, Victoria Crossover Box, Willesden Euroterminal site
- Contractor
- SCS JV
- Type of works
- Construction, Tunnel segment delivery
- Estimated Start Date
- 11/10/2023
- Estimated End Date
- 30/08/2025
What we are doing
We are adjusting the delivery hours of tunnel segments from our Flat Iron site to the Willesden Euroterminal site and Willesden Euroterminal site to Victoria Crossover Box site. The new hours will change from Monday to Saturday 8am to 6pm to Monday to Saturday 6am to 4pm and if required Sundays 6am to 4pm.
These changes are being made to better fit our tunnelling operations. This means that you may notice lorries using Old Oak Lane and Victoria Road earlier to and from our Flat Iron, Willesden Euroterminal and Victoria Road Crossover Box sites in the Old Oak area.
We will continue to advise our lorry drivers to adhere to safe road practices and be mindful of the community during early hours.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]