Tunnel segment deliveries by road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Traf-1-01/05/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- West Ruislip
- Worksite Name
- West Ruislip
- Contractor
- SCS JV
- Type of works
- Tunnel segment delivery
- Estimated Start Date
- 02/05/2024
- Estimated End Date
- 31/05/2024
What we are doing
What we are doing
We are writing to update you on how tunnel segments are delivered to our West Ruislip site. We normally use the rail siding at the site for segment deliveries, but are currently unable to do so until a safety audit has been completed.
To maintain supply of segments to construct the tunnels, we will need them to be delivered to West Ruislip by road from Thursday 2 May using our approved lorry routes.
We are not sure how long we will need to make deliveries by road but we will keep you informed.
How these works might affect you
Lorry movements for segment deliveries will be included in the existing limit of 550 lorry movements per day in Hillingdon.
Most tunnel segment deliveries will take place during core working hours (Monday to Friday 8am to 6pm, Saturday 8am to1pm). However, there may be some HGV movements outside core hours.
We would like to apologise for any disruption or inconvenience these deliveries may cause. Every effort is being taken to ensure that these deliveries are conducted in the least impactful way. We will ensure that disruption is kept to a minimum.