Tunnelling works set to begin in North Warwickshire

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Tun-45-29/05/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Water Orton
Contractor
BBV JV
Type of works
Tunnelling
Estimated Start Date
15/06/2023
Estimated End Date
31/12/2025

What we are doing

Construction of a 3.5 mile long tunnel in Birmingham is scheduled to start mid-June 2023. The tunnel boring machine (TBM) will bore a combined length of 7 miles, creating 3.5 miles of twin-bore tunnel between Water Orton in North Warwickshire and Washwood Heath in Birmingham. This phase is expected to be completed by late 2025.

As part of the works, we will need to transport material generated by the TBM across the Attleboro Lane plant crossing for re-use in the area between Water Orton Village and the nearby M6/M42 motorway link roads. The material will be excavated from the ground 24 hours a day by the TBM, apart from over holiday shutdown periods and planned maintenance. This activity will take place for both tunnels, the first of which is scheduled to start mid-June 2023. The second TBM is expected to launch in early 2024.

Between June 2023 and late 2025 we will continue to work 24 hours a day, seven days a week, in line with Section 61 of the Control of Pollution Act 1974. We will put in place all reasonable measures to control the levels of noise, vibration and dust during our on-site operations.