Twyford construction compound and archaeology

Work item: FUS_AWN_0155 HS2-EWFusion -Ph1-Ar-Ce-C1-Eco-7-30/11/2020

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Calvert, Steeple Claydon
Contractor
Fusion JV
Type of works
Archaeology, Fencing, Worksite / compound set-up
Estimated Start Date
29/01/2021
Estimated End Date
30/06/2021

What we are doing

As part of our continuing works ahead of the construction of the railway
we need to undertake some further work in your area, these works will
consist of:
• Construction of a small compound
• Boundary fencing
• Archaeological investigations