Twyford – Newton Purcell early works
Work item: HS2-EW-EK-Ph1-Ar-So-S2-Site-07-08/09/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Newton Purcell, Turweston
- Contractor
- EKFB JV
- Type of works
- Ground investigations, Utility works / surveys, Worksite / compound set-up
- Estimated Start Date
- 30/10/2020
- Estimated End Date
- 31/08/2021
What we are doing
We are undertaking early construction works to prepare the area for the
HS2 route. This activity will include:
1. Ground Investigation (GI) works
2. Utility works including trial holes
3. Setting up of works compounds
4. Localised clearance of vegetation and fencing
5. Haul road, access roads and drainage activities
6. Excavation, movement and storage of earthworks