UK Power Networks: electricity cable connection in Camden streets
Work item: UK Power Networks
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Camden Street, Delancey Street, Park Village East north, Pratt Street
- Contractor
- UK Power Networks
- Estimated Start Date
- 19/10/2023
- Estimated End Date
- 03/11/2023
What we are doing
From 19 October to 3 November 2023 UK Power Networks to carry out works of installing a new connection to the electricity network in the Camden area to reinforce the network. There will be small excavation sites on the following streets:
- Pratt Street – 19 October to 1 November
- Georgianna Street – 20 October to 2 November
- Camden Street – 23 to 28 October
- Delancey Street – 24 October to 3 November
- Park Village East – 25 October to 3 November
Working hours of Monday to Friday 8am to 5pm. There may be times when weekend working is required however will minimise these shifts where possible.
Traffic management measures will remain in place for the duration of our works. This work should not have any impact on your electricity supply. In the event of any difficulties, please contact UK Power Networks customer care team on 0800 028 4587 or [email protected].
For further details please see notification and traffic management plans for each street below.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]