Skip to main page content
View route map

UK Power Networks weekend works on North Gower Street-Starcross Street

Work item: UK Power Networks

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, North Gower Street, Starcross Street
Contractor
UK Power Networks
Estimated Start Date
20/08/2022
Estimated End Date
25/09/2022

What we are doing

UK Power Networks are in process of installing a new connection to the electricity network in the Camden area to reinforce our network.

Works will be carried out at the junction of North Gower Street and Starcross Street during the weekends on Saturday 20th to Sunday 21st of August and Saturday 24th September to Sunday 25th September. Working hours: Saturday 8am to 6pm and Sunday 9am to 5pm.

The work will involve digging a trench to install ducts that will then carry our power cable. Traffic management will remain in place for the duration of our works.

Work should not have any impact on residents electricity supply. In the event of any difficulties, please contact Modus Utilities Project Manager, Nick Bailey, on 07850 320557

For further details please see notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]