UK Power Networks works at Willesden Euroterminal
Work item: HS2-MW-UKPN-Ph1-S1-Prog-works-1-08/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- London, Old Oak and North Acton
- Location
- Willesden Euroterminal
- Worksite Name
- Willesden Euroterminal site
- Contractor
- UK Power Networks
- Type of works
- Installation Works
- Estimated Start Date
- 27/02/2023
- Estimated End Date
- 03/03/2023
What we are doing
In order to deliver power to the Tunnel Boring Machines, UK Power
Networks (UKPN) need to carry out electricity cable installation works
within the Willesden Euro-terminal (WET) site.
We will be working on the logistics bridge in the WET site installing
electricity cable ducts. As the bridge is operational during the weekdays
and weekend during the day, we will be undertaking our works during
the night. We will be working from Monday 27 February evening until
Friday 3 March, between the hours of 6pm and 6am, and will limit any
breaking out of concrete to finish by 11pm.
We will install acoustic blankets to minimise the noise levels as much as
possible.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]