UK Power Networks works at Willesden Euroterminal

Work item: HS2-MW-UKPN-Ph1-S1-Prog-works-1-08/02/2023

Work Item Summary

Project Phase
Phase 1
Region
London, Old Oak and North Acton
Location
Willesden Euroterminal
Worksite Name
Willesden Euroterminal site
Contractor
UK Power Networks
Type of works
Installation Works
Estimated Start Date
27/02/2023
Estimated End Date
03/03/2023

What we are doing

In order to deliver power to the Tunnel Boring Machines, UK Power
Networks (UKPN) need to carry out electricity cable installation works
within the Willesden Euro-terminal (WET) site.

We will be working on the logistics bridge in the WET site installing
electricity cable ducts. As the bridge is operational during the weekdays
and weekend during the day, we will be undertaking our works during
the night. We will be working from Monday 27 February evening until
Friday 3 March, between the hours of 6pm and 6am, and will limit any
breaking out of concrete to finish by 11pm.

We will install acoustic blankets to minimise the noise levels as much as
possible.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]