Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Oakley Square
- Contractor
- UK Power Networks
- Estimated Start Date
- 17/08/2022
- Estimated End Date
- 23/09/2022
What we are doing
UK Power Networks will be installing new cable ducts on Oakley Square area in three phases.
First section of works are planned to commence on Wednesday 17th August and complete on Thursday 25th August.
Second and third section of works are planned to commence on Monday 5th September and complete on Friday 23rd September.
Working hours: Monday to Friday between 8am and 6pm.
UK Power Networks has consulted with the local authorities and other relevant parties to ensure that the public experience as little
disruption as possible whilst our work takes place.
The works will consist of excavation of a cable trench in sections as the works progress along the route. Each section will be fenced off and acoustic barriers will be installed to limit noise. Traffic management in place with diversion signage for pedestrians and vehicles around the sites. Some parking bays will be suspended for the duration of these works.
Work should not have any impact on residents electricity supply. In the event of any difficulties, please contact Modus Utilities Project Manager, Nick Bailey, on 07850 320557
For further details please see notification below.