Skip to main page content
View route map

UK Power Networks works on Georgiana Street

Work item: UK Power Networks

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, Georgiana Street, Oakley Square
Contractor
UK Power Networks
Estimated Start Date
15/08/2022
Estimated End Date
26/08/2022

What we are doing

From Monday 15th August to Friday 26th August UK Power Networks will be installing new cable ducts on Georgiana Street.

Works will require a lane closure from the top of Georgiana Street at the junction for Lyme Street, down to number 22 Georgiana Street. There will be a two- way traffic management set up for the duration of these works.

Working hours: Monday to Friday between 8am and 6pm.

UK Power Networks has consulted with the local authorities and other relevant parties to ensure that the public experience as little
disruption as possible whilst this work takes place.

The works will consist of excavation of a cable trench in sections as the works progress along the route. Each section will be fenced off and acoustic barriers will be installed to limit noise. Traffic management in place with diversion signage for pedestrians and vehicles around the sites. Some parking bays will be suspended for the duration of these works.

Work should not have any impact on residents electricity supply. In the event of any difficulties, please contact Modus Utilities Project Manager, Nick Bailey, on 07850 320557

For further details please see notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]