UKPN Works at Willesden Euro-terminal site

Work item: HS2-MW-OTH-Ph1-Ar-So-S1-Prog-works-12-27/03/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Willesden Euroterminal
Worksite Name
Willesden Euroterminal site
Contractor
SCS JV, UK Power Networks
Type of works
Construction, Electrical Works
Estimated Start Date
14/08/2023
Estimated End Date
18/01/2024

What we are doing

From 14 August 2023 to 18 January 2024 UK Power Networks (UKPN) will be carrying out micro-tunnelling works to install electricity cables between Willesden Euro-Terminal (WET) site and the UKPN substation.

This involves excavating both sites to create a “launch pit” and a “receiving pit”. The launch pit will be located in the WET site and the receiving pit will be located in the UKPN substation site.

These works will not impact your electricity supply.