UKPN works at Willesden Euro Terminal site
Work item: HS2-MW-UKPN-Ph1-S1-Prog-works-2-16/02/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- London, Old Oak and North Acton
- Location
- Willesden Euroterminal
- Worksite Name
- Willesden Euroterminal site
- Contractor
- UK Power Networks
- Type of works
- Installation Works
- Estimated Start Date
- 04/03/2023
- Estimated End Date
- 27/03/2023
What we are doing
In order to provide power to the Tunnel Boring Machines, UK Power Networks (UKPN) need to carry out electricity cable installation works within the Network Rail site adjacent to Channel Gate Road, Willesden.
UKPN will be installing electricity cable ducts by excavating and undertaking open cut trenching.
UKPN will be working for three consecutive weekends: Saturday 4 March from 3pm to Monday 6 March 3pm; Saturday 18 March from 3pm to Sunday 19 March 10:30pm; and Saturday 25 March from 3pm to Monday 27 March 3pm.
The works will be continuous during these times. The timings have been agreed with Network Rail to minimise disruption to train schedules whilst we work around their tracks.
Download information relating to these works