Upcoming ground investigation surveys near A452 Chester Road, Birmingham
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-46-22/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Birmingham
- Worksite Name
- A452 Chester Road
- Contractor
- BBV JV
- Type of works
- Ground investigations, Traffic management
- Estimated Start Date
- 12/09/2022
- Estimated End Date
- 07/10/2022
What we are doing
We intend to carry out ground investigation (GI) works along the Cadent Gas line located off Tameside Drive and along a section of A452 Chester Road. These GI works will allow us to determine and better understand the ground conditions as well as help establish the exact locations of existing utilities.
The overnight works are scheduled to be undertaken weeknights from Monday 12 September 2022 until Friday 7 October 2022. There will be single lane closures in operation overnight from 9pm to 6am. Our working hours will be Monday to Friday 9pm to 6am. Our workforce maybe onsite one hour before and one hour after to set up and secure our equipment. To allow us to carry out these works safely and with least possible disruption to traffic and the local community, single lane closures will be in place along the A452 Chester Road, starting on both the northbound and southbound carriageway at the same time.
Please note these dates are indicative and are subject to change at short notice.