Upcoming works along A425 Leamington Road, Southam

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-38-13/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Southam
Contractor
BBV JV
Type of works
Utility works / surveys
Estimated Start Date
13/06/2022
Estimated End Date
29/07/2022

What we are doing

Planned works along sections of A425 Leamington Road

Two-way temporary traffic lights are planned to be in operation along sections of A425 Leamington Road, as shown on location plan overleaf, from Monday 13 June 2022 until Friday 29 July 2022, 24 hours a day, each day, including weekends.

This is to allow us to carry out utility diversions ahead of the temporary re-alignment of the carriageway and to construct the green tunnel.

The temporary traffic lights are required 24 hours of the day due to open excavations at the side of the carriageway and to conform to current safety standards.