Upcoming works along section of B4118 Birmingham Road
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-23-16/11/2023
Work Item Summary
- Project Phase
- Phase 1
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Haul road construction
- Estimated Start Date
- 04/03/2024
- Estimated End Date
- 28/02/2026
What we are doing
We need to create a controlled crossing on B4118 Birmingham Road, Water Orton for our haul road. Haul roads are temporary roads provided within a working area to allow for the movement of construction materials, construction machinery and/or construction staff around work sites. Haul roads are Balfour Beatty Vinci’s preferred logistical transport linkas they reduce the number of vehicles interfering with the existing road network and provide the most effective, efficient and safe possible control over essential operational works.
To create this controlled crossing, we will be installing two-way traffic lights along section of the B4118 Birmingham Road, Water Orton, as shown on the location plan overleaf. These temporary traffic lights will be in place from Monday, 4 March 2024, 24 hours a day, 7 days a week for up to two years. Access will be maintained for all properties and Emergency vehicles.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]