Upcoming works at Westgate
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-50-11/09/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Hanger Hill
- Contractor
- SCS JV
- Type of works
- Worksite / compound set-up
- Estimated Start Date
- 30/11/2020
- Estimated End Date
- 31/12/2021
What we are doing
Works to set up our Westgate site
We will be building a ventilation shaft and headhouse at our Westgate site. From 2 December 2020, SCSJV will start works to set up the Westgate site. The following works are planned at this site from December 2020 and during early 2021:
Installation of worksite fencing, gates, and security
On-site surveys and inspections
Installation of monitoring equipment
Vegetation and site clearance within the site boundary
Piling works
Bulk excavation of material
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]