Update: Atlas Road Logistics Tunnel works

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-14/08/2023

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Atlas Road
Worksite Name
Atlas Road
Contractor
SCS JV
Type of works
Tunnelling
Estimated Start Date
29/08/2023
Estimated End Date
31/12/2023

What we are doing

The first phase of the tunnelling works, where we simultaneously tunnelled and built the rear TBM components, has now been completed and the TBM is fully constructed.

From 29 August 2023 to December 2023, we will start phase two of the ARLT tunnelling programme, connecting the Atlas Road site to the Old Oak Common Station site.

More information on the ARLT can be found at: https://www.hs2.org.uk/building-hs2/tunnels/atlas-road-logistics-tunnel/