Update: Atlas Road Logistics Tunnel works
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-14/08/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Atlas Road
- Worksite Name
- Atlas Road
- Contractor
- SCS JV
- Type of works
- Tunnelling
- Estimated Start Date
- 29/08/2023
- Estimated End Date
- 31/12/2023
What we are doing
The first phase of the tunnelling works, where we simultaneously tunnelled and built the rear TBM components, has now been completed and the TBM is fully constructed.
From 29 August 2023 to December 2023, we will start phase two of the ARLT tunnelling programme, connecting the Atlas Road site to the Old Oak Common Station site.
More information on the ARLT can be found at: https://www.hs2.org.uk/building-hs2/tunnels/atlas-road-logistics-tunnel/