Update: Atlas Road Roundabout works
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-2-26/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Atlas Road
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Traffic management
- Estimated Start Date
- 08/08/2022
- Estimated End Date
- 31/12/2022
What we are doing
Utility asset protection at the Atlas Road Roundabout
Throughout 2021/22, HS2 contractor CSJV have been carrying out works at the Atlas Road roundabout to provide protection to utility assets prior to the construction of the Atlas Road Logistics Tunnel (ARLT).
Please see the link below for frequently asked questions in relation to the ARLT.
https://www.hs2.org.uk/wp-content/uploads/2022/07/2207-Atlas-Road-Logistics-tunnel-FAQs-final_.pdf
From summer 2022, these works at the Atlas Road roundabout will transfer from CSJV to the SCSJV contractor These works had been programmed to finish in Autumn 2022. Unfortunately, there have been delays due to various complications, for example obstacles below ground, which have resulted in delays to the delivery programme.
The current programme of works is due to be completed by SCSJV (once handed over to us) by the end of this year.
What to expect
Until the end of 2022, temporary traffic management will be in place during various phases on the Atlas Road roundabout and adjacent roads.
These works will include commissioning and abandonment works for the water and gas assets below ground as well as relining the current sewer structure. Excavation works will be required but are not expected to be as significant as the previous works.
You can view more information about the location of these works on the following pages.