Update: Delayed opening of Rabournmead Drive Park

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-02/12/2022_5

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
Rabournmead Drive
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
10/03/2023
Estimated End Date
31/03/2023

What we are doing

We planned to re-open all of Rabournmead Drive Park on 10 March. However, our works have been delayed by the recent wet and cold weather. We now need to keep an area of the park closed until 31 March to allow for the reinstatement of this area and any reseeding of grass to be undertaken. If this area does improve we may be able to open this sooner.