Update: Drainage works on Canterbury Terrace and retaining wall works

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-24/10/2022

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Canterbury Road
Worksite Name
Canterbury Works
Contractor
SCS JV
Type of works
Road closure
Estimated Start Date
26/10/2022
Estimated End Date
14/11/2022

What we are doing

We notified you in September 2022 regarding drainage works on Canterbury Terrace at the Junction with Albert Road and works to replace the existing wall along the north-western boundary between our site and Carlton House. These works were planned to be completed by the end of October 2022. Due to unforeseen circumstances these works will now been extended. Please find further details below.

Drainage works extension on Canterbury Terrace / Albert Road
We are continuing works to install new ducts and sewer connections below ground on Canterbury Terrace / Albert Road in preparation for the new train line. Due to unforeseen delays these works have been extended and will now be completed by 14 November 2022.

Works will take place between the hours of 8am to 6pm Monday to Friday and 8am to 1pm on Saturdays.

Once we have completed the underground works, we will backfill the trench and relay the tarmac and reopen the section of road.
Your utilities will not be affected during these works.

To help reduce noise during these works, were possible we will erect acoustic barriers and continue to monitor our working methods to ensure good practices are adhered to and any disruption is kept to a minimum.

We apologise for any inconvenience you may experience during these works.

Temporary road changes during the drainage works
Throughout these works a vehicle diversion will be in place and clearly signed. A map showing the diversion can be found below. We will continue to temporarily suspend eight parking bays at the northwest end of Canterbury Terrace and two parking bays at the eastern end of Albert Road. We will evaluate the suspended bays to see if some can be reinstated sooner during the works.
Our workforce has also been briefed and reminded as to not park in the available residential bays and to ensure available bays are kept clear of work equipment.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]