Update: extended hours for grouting at Mandeville Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-15/07/22_03
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Grouting
- Estimated Start Date
- 07/11/2022
- Estimated End Date
- 04/12/2022
What we are doing
What we are doing
We wrote to you in September to let you know that we would be continuing our grouting on the lower level of the Mandeville Road site seven days a week. To view this notice please click here
From 7 November to 4 December 2022, we will extend our working hours for grouting from 8pm until 10pm Monday to Friday.
This extension will allow us to run two shifts a day, which will help us to maintain our programme, and mitigate the effects of the recent and expected heavy rain on our productivity.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We will ensure that disruption is kept to a minimum.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]