Update: extended working hours at Canterbury Works site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog works-1-2/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Network Rail Possession/Closure
- Estimated Start Date
- 06/08/2022
- Estimated End Date
- 28/08/2022
What we are doing
Network Rail enhancement work extended hours
Works are ongoing within the Network Rail land at the north end of the site, opposite the rail tracks, in preparation for future works. These works need to be carried out overnight when trains are not running, to ensure the safety of staff.
The following dates and times for extended working hours have been agreed with Network Rail and Brent Council.
• 7pm on 06 August to 12pm on 07 August 2022
• 7pm on 13 August to 12pm on 14 August 2022
• 7pm on 20 August to 12pm on 21 August 2022
• 7pm on 27 August to 12pm on 28 August 2022
We do not anticipate these works to be disruptive, but you may hear additional noise from vehicle movements, the use of tools and construction plant usage. Additionally, task lighting will be in place near the railway tracks.
For more information about these works, please see the previous notification at https://assets.hs2.org.uk/wp-content/uploads/2022/03/1403-Update-of-works-at-Canterbury-Works-site.pdf
Dates and times mentioned in this notification may change and works rescheduled. We will keep the local community updated via post and at www.hs2.org.uk/in-your-area/map/