Update: Extended working hours at Canterbury Works site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-13/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- Network Rail
- Type of works
- Extended working hours
- Estimated Start Date
- 24/09/2022
- Estimated End Date
- 05/11/2022
What we are doing
Network Rail enhancement works extended hours
Works are ongoing within the Network Rail land at the north end of the site, opposite the rail tracks, in preparation for future works. These works need to be carried out overnight when trains are not running, to ensure the safety of staff.
The following dates and times for extended working hours have been agreed with Network Rail and Brent Council:
• 9pm on 24 September to 8am on 25 September 2022
• 12am to 7am on 2 October 2022
• 12am to 7am on 9 October 2022
• 12am to 7am on 16 October 2022
• 12am to 7am on 23 October 2022
• 8pm on 5 November to 12pm on 6 November 2022
We do not anticipate these works to be disruptive, but you may hear additional noise from vehicle movements, the use of tools and construction plant usage. Additionally, task lighting will be in place near the railway tracks.
We will continue to monitor our working practices throughout these works to ensure that any disruption is kept to a minimum.
Dates and times mentioned in this notification may change and works rescheduled. We will keep the local community updated via post and at www.hs2.org.uk/in-your-area/map/
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]