Skip to main page content
View route map

Update: Further works on the Adelaide Road site boundary

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-36-04/01/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden
Contractor
SCS JV
Type of works
Construction, Traffic management
Estimated Start Date
19/04/2021
Estimated End Date
03/05/2021

What we are doing

Removal of the brick wall on Adelaide Road

From 19 April 2021 for up to two weeks, we will be removing the section of brick wall next to the eastern end of our site. This will take place while temporary traffic management is in operation.

We are extending our site at the eastern end as we require additional space for construction of the ventilation shaft and headhouse. We need to remove this section of the wall in order to install our welfare cabins and access gates to the site. We will provide further updates as the works progress.

We will replace the wall when our works are completed. The new wall will have a permanent access point for emergency vehicles and for maintenance to the ventilation shaft and headhouse. We are planning to engage with you further about the design of the future wall and give you the opportunity to provide feedback.

Upcoming works on Adelaide Road

During spring and summer 2021, we will be carrying out further utility surveys and utility works on Adelaide Road. We are still confirming the dates and will write to you shortly with more information.

Information from our recent community update event

We held an online community update on 25 February. You can view the information we presented at the event via the Works in your area page at HS2inCamden.co.uk. We have also updated our Q&As about upcoming works at the Adelaide Road site, which you can view via the Works in your area page.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]