Update: Gas main protection works on West Gate
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-2-8/02/24_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Westgate
- Worksite Name
- Westgate
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 06/02/2024
- Estimated End Date
- 20/08/2024
What we are doing
West Gate Gas Diversion
We wrote to you in January, to tell you about the utility works that started on 6 February and were due to be completed on 7 June 2024.
Once we started the works, we realised that the condition of the gas main was worse than expected. Coordinating with the utility provider also contributed to the delays with these works.
Works are now due to be completed by 20 August 2024. There will be a combination of overnight and daytime working from 8pm to 6am and 8am and 8pm.
You can view the previous notifications on the HS2 in your area map via the HS2 in Brent and Ealing webpage here: www.hs2.org.uk/in-your-area/local-community-webpages/hs2-in-brent-and-ealing/
How will this affect you
We will create temporary changes on West Gate to ensure the safety of the public and our staff. This will include a footpath closure, lane closures and parking bay suspensions.
We will use noise reducing barriers where possible to help minimise noise, working as efficiently as possible whilst keeping our work areas safe and tidy.
Speak with our local engagement team
Our local engagement team is happy to arrange a time to speak with you by phone if you have any questions.
Please contact the HS2 Helpdesk using the contact details below to arrange this.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]