Update: Gas main protection works on West Gate

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-2-8/02/24_02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Westgate
Worksite Name
Westgate
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
06/02/2024
Estimated End Date
20/08/2024

What we are doing

West Gate Gas Diversion
We wrote to you in January, to tell you about the utility works that started on 6 February and were due to be completed on 7 June 2024.

Once we started the works, we realised that the condition of the gas main was worse than expected. Coordinating with the utility provider also contributed to the delays with these works.

Works are now due to be completed by 20 August 2024. There will be a combination of overnight and daytime working from 8pm to 6am and 8am and 8pm.

You can view the previous notifications on the HS2 in your area map via the HS2 in Brent and Ealing webpage here: www.hs2.org.uk/in-your-area/local-community-webpages/hs2-in-brent-and-ealing/

How will this affect you
We will create temporary changes on West Gate to ensure the safety of the public and our staff. This will include a footpath closure, lane closures and parking bay suspensions.

We will use noise reducing barriers where possible to help minimise noise, working as efficiently as possible whilst keeping our work areas safe and tidy.

Speak with our local engagement team
Our local engagement team is happy to arrange a time to speak with you by phone if you have any questions.

Please contact the HS2 Helpdesk using the contact details below to arrange this.