Update: ground investigations in Alperton Lane area
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-04/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Ground investigations
- Estimated Start Date
- 21/03/2022
- Estimated End Date
- 25/03/2022
What we are doing
Ground investigation works from 21 March
We recently wrote to you in October last year about ground investigation works in the Alperton Lane area.
These works did not go ahead in late 2021 and have now been rescheduled and will take place from 21 to 25 March between 8am to 6pm on Mondays to Fridays.
The ground investigation works will involve drilling two holes into the ground and installation of monitoring equipment below ground on the main sewage pipes. We are installing the monitoring equipment so we can monitor the condition of the sewage pipes while we build the HS2 tunnels.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]