Update: Hampstead Road utility diversion works
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-1-14/02/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Hampstead Road
- Worksite Name
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- Utility Works
- Estimated Start Date
- 19/02/2025
- Estimated End Date
- 29/08/2025
What we are doing
Hampstead Road southern section update – 19 February to August 2025
We are continuing our utility works in the southern section of Hampstead Road, near Varndell Street. On 19 February, we will move to the next phase of traffic management, during which Varndell Street will remain closed and we will close the northbound lane on Hampstead Road. We previously informed you that this would be on 17 February.
Mace Dragados JV (MDjv) will continue their utilities works at the junction of Cardington Street until early April. Due to the traffic management on Cardington Street, we will need to close the footpath on Hampstead Road from the current pedestrian crossing point up to Varndell Street until MDjv complete this work. We will install another crossing point at the junction with Varndell Street to maintain access for pedestrians. See footpath diversions and crossing points on the map below. We will maintain two way traffic on Hampstead Road using temporary traffic lights. Vehicle access to Regent’s Park estate will be via Robert Street.
We will continue to monitor the traffic management and reduce impacts where possible. We apologise for any disruption caused.
Please see the link below for further information.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]