Update: Installation of electricity cables
Work item: HS2-EW-UT-Ph1-Ar-So-S1-UT-18-20/03/2021_02
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Kilburn
- Contractor
- UK Power Networks
- Type of works
- Utility works / surveys
- Estimated Start Date
- 06/04/2021
- Estimated End Date
- 30/06/2021
What we are doing
UK Power Networks Update
Our notification in December 2020 advised that works would be ongoing during January to June 2021. You can find our previous notification below:
Electricity cable installation – Canterbury Road notification, 15 January 2021 to June 2021.
Works are required for reinstatement of a cable trench on Rudolph Road, Kilburn Park Road and Carlton Vale during the weekends below. Works are due to commence on the 6th of April and works are planned to reinstate the trench evacuated during the previous week between the hours of 8am and 1pm on the Saturdays noted below. Dependent on works progress we may not utilize all the weekends noted. The area will be fenced off and acoustic barriers will be installed to limit noise impacts. Works will be undertaken on the following dates:
Saturday (10/04/21, 17/04/21, 24/04/21 & 01/05/21)
Tarmac cable trench
The work, in partnership with our contractor Modus Utilities, is needed to provide a new electricity connection for the HS2 Project.
We apologise for any inconvenience caused and will make every effort to minimise any impact on your community. In the event of any difficulties, please contact Modus Utilities Project Manager, Craig Sheehy, on 07850 320536.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]