Update: Installation of electricity cables

Work item: HS2-EW-UT-Ph1-Ar-So-S1-UT-18-20/03/2021_02

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Kilburn
Contractor
UK Power Networks
Type of works
Utility works / surveys
Estimated Start Date
06/04/2021
Estimated End Date
30/06/2021

What we are doing

UK Power Networks Update

Our notification in December 2020 advised that works would be ongoing during January to June 2021. You can find our previous notification below:

Electricity cable installation – Canterbury Road notification, 15 January 2021 to June 2021.

Works are required for reinstatement of a cable trench on Rudolph Road, Kilburn Park Road and Carlton Vale during the weekends below. Works are due to commence on the 6th of April and works are planned to reinstate the trench evacuated during the previous week between the hours of 8am and 1pm on the Saturdays noted below. Dependent on works progress we may not utilize all the weekends noted. The area will be fenced off and acoustic barriers will be installed to limit noise impacts. Works will be undertaken on the following dates:

Saturday (10/04/21, 17/04/21, 24/04/21 & 01/05/21)

 Tarmac cable trench

The work, in partnership with our contractor Modus Utilities, is needed to provide a new electricity connection for the HS2 Project.

We apologise for any inconvenience caused and will make every effort to minimise any impact on your community. In the event of any difficulties, please contact Modus Utilities Project Manager, Craig Sheehy, on 07850 320536.