Update: Installation of electricity cables

Work item: HS2-EW-UT-Ph1-Ar-So-S1-UT-18-20/03/2021_04

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Canterbury Road
Contractor
UK Power Networks
Type of works
Utility works / surveys
Estimated Start Date
15/05/2021
Estimated End Date
29/05/2021

What we are doing

Update: Installation of electricity cables
Our recent notification advised that works would be ongoing during January to June 2021. You can find our previous notification below

Electricity cable installation – Canterbury Road notification, 15 January 2021 to June 2021.

Works are required for excavation of a cable trench within the HS2 SCS site at Canterbury Road during the weekends below. The area will be fenced off and acoustic barriers will be installed to limit noise impacts. Works will be undertaken on the following dates:

Saturday (15/05/21, 22/05/21 & 29/05/21)

 Excavate cable trench within site boundary
 Install ducts within trench
 Backfill trench with sand & stone

The work, in partnership with our contractor Modus Utilities, is needed to provide a new electricity connection for the HS2 Project.
We apologise for any inconvenience caused and will make every effort to minimise any impact on your community. In the event of any difficulties, please contact Modus Utilities Project Manager, Craig Sheehy, on 07850 320536.

 

 