Large load movements from Vehicle Holding Area
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Traf-1-09/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Prince Albert Road
- Worksite Name
- Euston Approaches, Vehicle Holding Area
- Contractor
- SCS JV
- Estimated Start Date
- 12/09/2022
- Estimated End Date
- 30/09/2022
What we are doing
Cabins removal from Vehicle Holding Area (VHA).
Please be aware that planned large loads collection from the Vehicle Holding Area on Prince Albert Road are postponed from 17 September to 24 September.
For further details please see notification below.
Large load deliveries and collections to worksites via VHA.
There will be large loads being delivered to various work sites via Hampstead Road and Prince Albert Road on the following dates:
- Tuesday 20 September
- Friday 23 September
- Saturday 24 September
These loads need to be moved at night or early morning or on weekends outside of peak hours for safety reasons. Due to the size and weight of these movements there may be occasions where our approved lorry routes are not suitable, and the haulier may need to use alternative roads. Our traffic management team will be present to assist the haulier to safely navigate the route.
For details please see the large load movements notification below.
Download information relating to these works
- Cabins removal from VHA on 24 September
- Large load movements - September
- Cabins removal from VHA on 17 September
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]