Update notice of Crossrail Depot and utility protection slab works on Old Oak Common Lane
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-32-30/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Excavation works, Piling, Vegetation clearance
- Estimated Start Date
- 04/05/2022
- Estimated End Date
- 31/01/2023
What we are doing
Vegetation removal
We previously notified you of work to the substation relocation and the fence replacement on Old Oak Common Lane. We are writing to update you on these works.
Works have started on the fence installation and we have begun to clear the vegetation in the area. This is to prepare the area for the construction of Old Oak Common Station, as part of our ongoing works. This work will take place during our core working hours, and will be complete before the end of June.
Substation relocation and Crossrail Depot fence works
Since May we have been working towards moving an old substation, which is located opposite Kildun Court, further up Old Oak Common Lane near the Crossrail Depot. The area is shown on the map on page 2.
This work requires a single lane road closure so excavation and piling can take place. The single lane road closure will start by Kildun Court and move up towards the Crossrail Depot as the works progress. Work includes rerouting the substation cables and replacing the fence by the Crossrail Depot. To support the work, we will be using large machinery and a crane. Lorries will be used to take away the excavated material.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]