Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Adelaide Road, Camden
- Worksite Name
- Adelaide Road
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 13/09/2021
- Estimated End Date
- 17/09/2021
What we are doing
Drainage surveys at Sunny Mews
We wrote to you previously about drainage surveys in the carpark of Sunny Mews between 16 and 20 August 2021. The surveys have been rescheduled to 13 to 17 September.
We will visit between 8am and 6pm to carry out the surveys. We will access the drainage via a manhole located in the parking area of Sunny Mews and use a camera to investigate the condition of the drainage.
Our surveying team may need to flush the drainage using a high-pressure water jet. There will be parking bay suspensions in place on Gloucester Avenue and a water tanker will be parked here in case we need to flush the drainage.
The dates for the surveys may change.
Drainage surveys in St George Camden Goods Yard development site
From 13 to 17 September, we are also planning to carry out a drainage survey via a manhole in the St George Camden Goods Yard Development site. Our surveyors will visit this site to carry out surveys between 8am to 6pm to carry out surveys. We have agreed these surveys with the developer.