Update: Notice of environmental works on land off Yarlet Lane and Marston Lane, Marston
Work item: HS2-MW-BBV-Ph1-Ar-No-Eco-43-30/01/2023
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- Marston Lane, Yarlet Lane
- Worksite Name
- Marston Lane
- Contractor
- Balfour Beatty
- Type of works
- Early Environmental Works, Environmental mitigation works, Tree planting
- Estimated Start Date
- 18/02/2023
- Estimated End Date
- 25/03/2023
What we are doing
As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.
We will be planting 180,000 tree and hedge plants along the route, and approximately 8,000 of these will be planted off Yarlet Lane and Marston Lane. There is a short window of opportunity during February and March when we can carry out this work.
To do this, we will be planting on six consecutive Saturdays from 18 February to 25 March 2023. We will work between 8am and 4pm, this will be in addition to the normal working week Monday to Friday between 8am and 6pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]