Update: notice of environmental works to land north of Bishton Lane, Moreton

Work item: HS2-EW-BB-Ph2A-Prog-works-12-31/05/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Bishton Lane, Moreton
Worksite Name
Bishton Lane, Moreton
Contractor
Balfour Beatty
Type of works
Early Environmental Works, Environmental mitigation works
Estimated Start Date
18/07/2022
Estimated End Date
30/04/2023

What we are doing

As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.

We have recently finished the archaeological trial trenches on land to the north of Bishton Lane. We will now start work to create ecological mitigation ponds. We will surround the ponds with grassland habitat that we will create as part of the work. We will use the ponds to relocate any protected species, such as Great Crested Newts before we need to remove any other habitats.

When the work will take place

We will start the excavation of the ponds on 18 July 2022, and the work will be ongoing throughout the year ready for planting the aquatic plants in them in autumn.

The timeline for the works is shown below:

  • Mitigation pond creation – July ’22 to November ‘22
  • Grassland creation – September ‘22 to October ‘22
  • Bat house construction – December ’22 to April ‘23
  • Demobilisation – April ‘23