Work item: Reference number: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-20-12/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Wormwood Scrubs
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Excavation works, Tunnelling, Utility works / surveys
Estimated Start Date
06/06/2022
Estimated End Date
15/09/2022

What we are doing

Excavation and Reinforced Concrete Works in Wormwood Scrubs
We will be excavating a launch shaft to prepare the area to launch the micro-tunnelling machines. As part of this work, we will also be installing concrete structures in the ground to enable the micro-tunnelling to be carried out.
To complete this work an excavator will dig to the pit. All material will be removed from site using tipper lorries. Once the excavation is complete, we will install a concrete base slab with front and back walls.
Micro-tunnelling works in Wormwood Scrubs
Once the shaft is complete, we will be installing eight micro-tunnels, which will run from the launch chamber in Wormwood Scrubs site underneath the railway tracks to the reception chamber in the main site. These micro-tunnels will be used to divert the services along Old Oak Common Lane. This diversion is needed to allow us to lower Old Oak Common Lane that is planned in the future.

Download information relating to these works