UPDATE – Notice of night shift works – Berkswell Station

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-25-02/01/2022

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
Berkswell
Worksite Name
Truggist Lane
Contractor
BBV JV
Type of works
Piling
Estimated Start Date
27/02/2022
Estimated End Date
10/04/2022

What we are doing

We previously notified you that BBV will be carrying out preparatory works, on the West Coast Main Line near to Berkswell Station on Saturday nights from 27 February to 10 April. Following feedback from the community we will be suspending the works this weekend (26 and 27 March) in order to make changes to address the concerns that have been raised.

We plan to resume work the following weekend (2 April) where we will be using a pile driver to install the remaining steel pile foundations for the new overhead power line poles before the existing equipment can be dismantled and the new power line installed.

The West Coast Main Line will be closed between 10.00pm and 8.00am on each Saturday night. The workforce will access the railway through the rear of Berkswell Station car park and Truggist Lane compound.

We will keep you updated through www.hs2insolihull.co.uk.