Update: Notice of out of hours delivery at the Mandeville Road vent shaft site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-2-19/06/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Northolt
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Traffic management, Worksite / compound set-up
Estimated Start Date
09/08/2021
Estimated End Date
26/08/2021

What we are doing

What we are doing
We notified you in June about some expected out of hours deliveries at our Mandeville Road site. This has been rescheduled to facilitate the installation of the site offices.

From 9 to 26 August 2021, we will be taking delivery of sheet piles at the Mandeville Road vent shaft site, in the area shown on the map overleaf.  There will be two deliveries per evening outside of core working hours, between 8pm and 9pm. For safety reasons, we will temporarily stop traffic flow outside of our site to allow the lorries to reverse into site. Each delivery should take approximately fifteen minutes.

How the work might affect you
The traffic will be held by traffic marshals for 15 minutes to allow the lorries to reverse into site. Residents will hear lorries reversing up the access road and some flashing lights may be seen.  A crane will unload the lorries the following morning to avoid unnecessary noise out of hours.