UPDATE: Notice of road closures, Banbury Lane, Thorpe Mandeville
Work item: Reference number: HS2-EKFB-25-1033
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Thorpe Mandeville
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 10/11/2025
- Estimated End Date
- 30/11/2025
What we are doing
Between Thorpe Mandeville and Culworth we have been building the Lower Thorpe viaduct. Earlier this summer, the Lower Thorpe viaduct was launched over Banbury Lane. We are now progressing with the concrete works for the deck structure.
24 hours from 6am on the first day to 8pm on last day of the closure
• POSTPONED Monday 3 November to Wednesday 5 November
• NEW DATES Monday 10 November to Wednesday 12
November
• Monday 24 November to Sunday 30 November
The following dates are subject to change based upon the
construction schedule and weather. Updates will be made to this
notification online and at the roadside date boards.
• Wednesday 10 December to Friday 19 December
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]