Update notice of sheet piling work at Mandeville Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-13-20/07/2021_03
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Extended working hours, Piling
- Estimated Start Date
- 04/01/2022
- Estimated End Date
- 31/03/2022
What we are doing
Sheet piling
We wrote to you in November to let you know that we would be installing sheet piles at our Mandeville Road site until the 23 December 2021. The site will close for the festive period, from 24 December 2021 to 3 January 2022.
From 4 January to 31 March 2022, we will continue to install sheet piles at the northern end of our site in the areas shown on the map overleaf.
In order to bring our deliveries in safely, we’ll need to work a bit later two evenings a week – up until 8.30pm on a Tuesday and Thursday. This is an extension to our core working hours of 8am to 6pm Monday to Friday.
The additional hours on Tuesdays and Thursdays will be used for sheet pile deliveries outside of peak times to minimise the impact on traffic flow in the area.
Our site will be closed between 24 December 2021 and 3 January 2022 for the festive period and will reopen on 4 January 2022. During this period our cranes will be lowered and positioned horizontally.
How these works might affect you
You may experience increased construction noise during this period. Noise and vibration monitoring will be in place throughout these works. We will use water sprays to reduce dust generated by
construction activities.
We would like to apologise in advance for the disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.
What to expect
During the works, you may notice much larger construction equipment and machinery at our site
including heavy goods vehicles, sheet piles, excavating machinery and cranes.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]