Update – Notice of Traffic Management, Steeple Claydon Road, Twyford Road, West Street and Gawcott Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-07-30/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Calvert, Steeple Claydon
- Worksite Name
- Gawcott Road, West Street
- Contractor
- EKFB JV
- Type of works
- Gas Main Works, Traffic management
- Estimated Start Date
- 05/02/2024
- Estimated End Date
- 07/04/2024
What we are doing
Since February 2024, we have been carrying out some works on the temporary gas main diversion by completing gas trial holes. These works are being completed under 4-way lights.
To carry out these works safely and effectively, there are traffic lights at the crossroads of Steeple Claydon Road, Twyford Road, West Street and Gawcott Road. These works are an important step towards the re-alignment of Gawcott Road/Perry Hill over the new bridge, currently under construction.
Update
Due to exceptionally wet weather conditions and delays to the works we need to keep the lights in place for an extended period. The lights will now be in place until Sunday 7 April except for Easter weekend. The lights will be removed by close of play on Thursday 28 March and will be back in position on Tuesday 2 April.
The current gas trail holes are planned to be completed by Thursday 28 March. We will then move to the opposite side of the carriage way to complete water trial holes.
When will these works take place?
Steeple Claydon Road, Twyford Road, West Street and Gawcott Road crossroads will be under traffic management from Monday 5 February until Sunday 7 April 2024 near to the EKFB compound.