Update- Notice of traffic management Welsh Road, Offchurch

Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Traf-37-06/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Offchurch
Contractor
BBV JV
Estimated Start Date
28/06/2021
Estimated End Date
24/07/2021

What we are doing

Due to unforeseen weather conditions, the working period has now been extended from 28 June to 24 July.

During the next month our programme of earthworks will begin in the area. Our works will involve excavating the ground, creating foundations for structures, and moving excavated material around the site to create environmental bunds.
To safely carry out these works we will install a controlled vehicle crossing on Welsh Road. This will allow our site vehicles and machinery to safely cross the road. During the installation of the vehicle crossing we need to install temporary traffic lights from 28 June to 24 July 2021.
Access will be maintained to all properties during these works