UPDATE: Notice of traffic management, Wormleighton Road, Boddington

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-18-09/12/2024

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Boddington
Contractor
EKFB JV
Type of works
Traffic management
Estimated Start Date
04/01/2025
Estimated End Date
31/07/2025

What we are doing

At the Banbury Road overbridge, near Boddington we are currently installing parapets to the bridge deck and building the foundations for the vehicle restraint system. We are preparing for the realignment of the Wormleighton Road over the new Banbury Road overbridge.

To complete these activities there will be a section of single lane traffic, managed by multi-way traffic lights on a section of Wormleighton Road near Stoneton Lane. When will these works take place?
Update: Saturday 4 January 2025 until 31 July 2025.