Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
A500, Hanchurch Interchange (M6 junction 15/A500)
Worksite Name
A500 Queensway, M6 J15
Contractor
Balfour Beatty
Type of works
Survey
Estimated Start Date
27/03/2023
Estimated End Date
26/04/2023

What we are doing

HS2 Ltd is proposing to make changes to the M6 Hanchurch Interchange at Junction 15, Newcastle Road, Clayton Road and the junction of Newcastle, Trentham and Whitmore Road, to improve the traffic flows during the construction of HS2.

During the detailed design stage of the process, we have identified four areas where further utility surveys are required.

Due to the location of these surveys, and to enable us to complete them safely, we will need to install traffic management during the work. We have worked hard to reduce the impact. However, there will be two-night shifts required to complete the work.

Resident access will also remain uninterrupted throughout.

The daytime surveys will be completed between

Monday 27 March to Tuesday 18 April 2023, 9:30am until 3:30pm

The night-time surveys will be completed on

Wednesday 12 April 2023 and Wednesday 26 April 2023, 8pm until 5.30am