Update notice of works at Mandeville Road site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-34-22/01/2022_02

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Borehole works, Excavation works, Road repairs
Estimated Start Date
23/05/2022
Estimated End Date
15/07/2022

What we are doing

What we are doing
As part of the ongoing works to prepare the site for the construction of the ventilation shaft and headhouse we will be doing further excavation on the embankment, drilling boreholes to manage water levels on site and resurfacing the access road.

From 23 May to 13 June 2022, we will be undertaking further excavation works at the eastern end of the embankment. This is the section closest to the Carr Road access track. We will be removing the surface that is currently in place in order to complete the new embankment down to the works area at railway level.

From 23 May to 15 July 2022, we will be drilling small boreholes to pump out excess groundwater to help manage the water levels on site during construction.

From 26 to 27 May 2022, we will be removing the old road surface and installing tarmac on the upper access road on site. You may smell the tarmac being laid during this time.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.