Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harefield
- Contractor
- SCS JV
- Type of works
- Ecological surveys
- Estimated Start Date
- 01/06/2021
- Estimated End Date
- 14/06/2021
What we are doing
What we are doing
We wrote to you in May to advise you that we would be carrying out ecological surveys on 17 May and 1 June along Newyears Green Lane in the area shown on the map below.
Due to poor weather conditions, we were unable to complete the surveys. We therefore require additional time to complete these works which will now be completed on 1 and 14 June 2021.
A road closure will be required between 8pm and 5am to ensure these works can be carried out safely.