- Type of works
- Cement pours, Excavation works
- Estimated Start Date
- 04/01/2022
- Estimated End Date
- 04/06/2022
What we are doing
What we are doing
We wrote to you in November 2021, to update you on the construction of the ventilation shaft at South Ruislip.
Works at our site will stop from 23 December 2021 to 3 January 2022 for the Christmas period. On 4 January 2022, work will continue as we construct the diaphragm wall for the shaft and excavate to 35 metres below ground level.
From 4 January 2022 to 4 June 2022, we will be excavating and concreting Monday to Friday 24 hours a day and Saturdays 8am to 8pm.
You may experience a period of increased construction noise during this period. Noise and vibration monitoring will be in place throughout these works. We will use water sprays to reduce dust generated by construction activities.